Question: 3

You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent. The IT manager adds an additional business driver that has a priority value set to 30 percent You need to create a new prioritization that includes the additional business driver. What should you do?

A. Create a new calculated prioritization. Select the drivers to priority.
B. Create a new manual prioritization. Select the correct department, and then select the drivers to prioritize.
C. Create a new manual prioritization. Select the drivers to prioritize, enter the value for each dnver, and then choose to normalize.
D. Create a new manual prioritization. Select the drivers to prioritize, and then rank the drivers sequentially.

Answer: A