70-348 | You are the Microsoft PPM administrator for a large…

Question: 3

You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent. The IT manager adds an additional business driver that has a priority value set to 30 percent You need to create a new prioritization that includes the additional business driver. What should you do?

A. Create a new calculated prioritization. Select the drivers to priority.
B. Create a new manual prioritization. Select the correct department, and then select the drivers to prioritize.
C. Create a new manual prioritization. Select the drivers to prioritize, enter the value for each dnver, and then choose to normalize.
D. Create a new manual prioritization. Select the drivers to prioritize, and then rank the drivers sequentially.

Answer: A

70-348 | An organization uses Microsoft PPM to manage projects…

Question: 2

An organization uses Microsoft PPM to manage projects. The organization tracks all projects by collecting time on tasks on a daily basis. You need to ensure that resources can enter their time on tasks.
Which three actions should you take? Each correct answer presents part of the solution.

A. On the Task Settings and Display page, set the tracking method to Hours of work done per period
B. On the Task Settings and Display page, select Resources should report their hours worked per day
C. On the Task Settings and Display page, clear the check box Force project managers to use the progress reporting method specified above for all projects.
D. On the Task Settings and Display page, select the check box Force project managers to use the progress reporting method specified above for all projects.
E. Instruct the project managers to select the tracking method for their project in Microsoft PPM.

Answer: A,C,D

70-348 | You use Microsoft PPM to manage an e-commerce portal…

Question: 1

You use Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level. You need to be able to see all programs and their associated individual projects from within Project Center. What should you do?

A. Select the Enterprise Project Type Name field as the value for grouping.
B. Select the Master Program field as the value for filtering.
C. Select the Subprojects check box.
D. Select the Project Details view.

Answer: C